Engineering / Ethiopia / ILRI / Official

Addis Engineering activities (19 – 20 Nov. 2016)

Engineering and Facility Unit has some activities over the weekend.

1. To make the site ready for external and site work,  areas  in front of new Gene Bank building will be cleaned on the 19 and 20 Nov. 2016.

In connection to this, staff are strictly advised to park their cars away from this location.

2. Cutting of asphalt in two locations as part of campus fire hydrant construction project during the coming two consecutive weekends will follow. This was last week’s plan but due to certain circumstances we have postponed the work  to Nov. 19 and 20, 2016.

This is to kindly inform you  that the main roads leading to Borena bldg. and residences will be closed during this time. So please use the main straight roads  through store, fuel station, Gene Bank, Zebu Club to access to both office and residence.

We will send more updates of the upcoming activities.

 

Adiskidan Abera | Civil and Ground Maintenance Works Supervisor